RapidRide R funding push puts South Seattle bus upgrades back in focus

The Oct. 15 announcement combines a budget proposal, a route-and-station ordinance sent to the County Council and a push to hire a design team.

Red and orange RapidRide transit bus moving on a tree-lined street

Smiling man with mustache in blue shirt against deep red background Headshot

King County Executive Girmay Zahilay is proposing $64.4 million in accelerated funding for the RapidRide R Line, a long-planned upgrade to Seattle's Route 7 that would bring faster buses and new station infrastructure to South Seattle.

The Oct. 15 announcement combines a budget proposal, a route-and-station ordinance sent to the County Council and a push to hire a design team. The package advances the project, but it does not mean the line is approved for immediate construction or that a new opening date has been set. The county's announcement still describes planned service by 2032.

The project has been in development since 2015. Its proposed corridor connects downtown Seattle and the Chinatown-International District with neighborhoods including Mount Baker, Columbia City and Rainier Beach, adding a connection to Rainier Beach Station.

For riders, the changes would extend beyond a new route name. Planned work includes more bus-only lanes, real-time arrival signs, upgraded shelters, lighting, sidewalks and curb ramps. Boarding changes are intended to make trips easier for people using wheelchairs and other mobility aids.

The route plan also makes a tradeoff familiar to bus rapid transit projects: fewer stops can speed service, but longer walks can create problems for existing riders. After hearing concerns from seniors, people with disabilities and families, the county added two stops back into the proposal, at Rainier Avenue South near State/Grand streets and South Bayview Street.

The proposed R Line would have 56 stops. Sixteen stops now served by Route 7 would not be served by RapidRide R; 12 would retain other bus routes, while the other four would be within 0.2 miles of a RapidRide stop, according to the county. Service south of South Henderson Street requires a separate planning process.

Detailed design remains early. The county says the project is at 10% design, with proposals for engineering, planning and design services due Nov. 5. Council hearings and two additional rounds of community engagement during design are still ahead.

The next test is whether the funding and alignment proposals can move through review while addressing the access concerns that have shaped the stop plan. For South Seattle riders, a faster corridor and a usable walk to the bus need to arrive together.